Project Process Overview

Project Process OverviewEWB-CPCProjects Committee

Action Duration Timeline
1 New or existing project is presented to EWB-CPC at monthly meeting The project representative from the NGO, community presents the potential project or need for
EWB-CPC at a monthly chapter meeting.
kick-off 0 weeks
2 EWB-CPC approves project to move forward with completing Project Application Form (#501 or #502)The project committee and executive committee approve the NGO or community to proceed with the Project Application Form,
and a leader is appointed/selected/volunteers.
two weeks 2 weeks
3 Project Team forms/grows.EWB-CPC is familiar with the project, the project team leader is selected, and the project team grows. 2 to 4 weeks 4 weeks
4 Project Team submits the Project Application Form two weeks before the TAC MeetingWith the help of the project team, the NGO and/or community complete the Project Application Form. The project team is
responsible for submitting the Project Application Form to TAC two weeks prior to a TAC meeting (posted on EWB-USA site).
2 to 4 weeks 8 weeks
5 TAC reviews Project Application Form: approves, rejects, requests more information 2 to 4 weeks 12 weeks
6 Project Team gathers info about community 2 weeks 14 weeksThe project team continues researching the community and the problem, considers any additionaly help that might be needed, etc. 2 weeks 14 weeks
7 Project Team prepares and presents Site Assessment Plans (#806) to TAC for approval (if not approved, needs more info)The project team prepares the Site Assessment Plans based on Site Assessment Form (#505) and presents the plans to the TAC
in the form of a presentation (#806).
2 weeks 16 weeks
5 TAC reviews Site Assessment Plans approves, rejects, requests more information
The project team prepares the Site Assessment Plans based on Site Assessment Form (#505) and presents the plans to the TAC
in the form of a presentation (#806).
2 to 4 weeks 12 weeks
8 Project Team prepares travel forms (#601, #603, #605) and reviews travel tips (#602)Once approved, the project team continues planning and preparing for the site assessment trip. 4 to 6 weeks 20 weeks
9 Project Team executes the site assessment trip and forms (#505, #509)The project team submits site assessment report (#507) within one month of returning. 1 to 2 weeks
4 weeks
22 weeks
26 weeks
10 Design of ProjectThe project team, along with EWB-CPC, designs the project. If necessary, a second site assessment may be planned. 20 weeks
2 weeks
42 weeks
around 36 weeks
11 Project Team prepares Implementation Progress Presentation (#807) for approval (#808)The project team prepares the Implementation Progress Presentation and presents it to the TAC via presentation. 2 weeks 44 weeks
12 Project Team prepares travel forms (#601, #603, #605) and reviews travel tips (#602)Once approved, the project team continues planning and preparing for the implementation trip. 2 weeks 46 weeks
13 Project Team executes the implementation trip and forms 2 weeks 48 weeks

All forms can be found on the EWB-USA website.

Project Process

Project Selection Criteria
Learn how EWB-CPC selects projects
Project Process Overview (15kB .pdf)
Learn how a project procedees after it is selected.